The Company is proposing a 2-phase, $1.18 million work program for ongoing exploration and development of the Ample-Goldmax Property.  A detailed summary of the budget for Phase I is provided below.     

Phase 1 Exploration Program

 

Geology and Prospecting Work

       $77,000

Drilling

       309,100

Assay & Geochemical Analysis

       102,630

Site Clean-up

           5,000

Accommodation, Travel Expenses, etc.

         24,000

Trenching

           5,000

Data Digitization

           4,000

Other Cost Reserve

         10,000

Administration

         53,673

Total Phase I

       590,403

Total Phase II

     $589,597 

Total of Phase I and II

$1,180,000 


Phase II work will consist of further diamond drilling on known structures; geochemical work on other sections of the Property; and geophysical programs on other sections of the Property.  The Phase II program will be based on the success of the Phase I program.